South Flank Mining Area C,
140km NW of Newman, WA
BHP
NRW
10 months
Nov-18
Oct-19
South Flank is located 156 kilometres north-west of Newman and nine kilometres south of BHP’s Mining Area C facility in the Pilbara region of Western Australia. Producing 145 million tonnes of iron ore each year, it will supply global steel markets for 25 years.
Melchor Contracting were engaged to complete the concrete package of two primary crushers on the South Flank project.
The concrete package for each crusher consisted of 1900 cubic meters of concrete. Due to 12m high walls, and a 1.5m thick suspended slab at 10m from the foundation level, Melchor Contracting designed and executed complex formwork systems. Melchor Contracting was responsible for all the permanent and temporary works through supply of labour, plant and materials.
Key Features:
Start laying the foundation for a career in Concreting with Melchor Contracting.
Read moreWe provide services that include head contracts, sub-contracting and labour hire to project owners, EPC contractors and Tier-1 civil contractors.
Get in TouchUnlock a world of diverse opportunities with a company that invests in their team’s growth and wellbeing.
Join our TeamMelchor Perth
Unit 1/3 McDonald Street
Osborne Park, WA 6017
Melchor Karratha
33 Oxide Loop
Karratha, WA 6714
Contact us